Date

Event
 March 17th - March 19th 2015      OnCore Immersion Training 
 March - August 2015 2015 Legacy Data Mapping and Migration 
 April 27th - 28th 2015 Super User Training 
 June 2nd, 2015 Test Environment Available 
 October 2015 Data Verification Complete 
 October - November 2015
General End User Training 
 October 27th, 2015 Production Go-Live (oncology only)
 Jan 2016 (Phase 2) eCRFs and Study Calendars Go-Live
 Coming in 2017-2018 (Phase 3) Non-oncology/Enterprise-wide Go-Live